Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the polylang domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/aspfl00rscp/public_html/staging.aspfloors.com/wp-includes/functions.php on line 6131
161 Castlereagh Street, Sydney - ASP Access Floors Skip to content
161 Castlereagh Street, Sydney

161 Castlereagh Street, Sydney

Sustainability was at the heart of the design of 161 Castlereagh Street. ASP’s Ultrafix system offered a sustainable, cost effective and functional solution.

Client

ANZ and Freehills

Builder

Built Holdings

Purpose & Size

Base Build Office Fit Out: 15,800m²

Duration

6 Months

Completed

October 2014

Project Features and Highlights:

161 Castlereagh Street has been designed to a 6 Star Green Star rating from the Green Building Council of Australia and offers modern, open plan, flexible workspace for employees to interact and collaborate.

The building design applies new technologies to deliver operational and environmental benefits, with sustainable materials being used throughout the fit-out. The ASP Access Floors system, complete with its own certified environmental audit, ensured the sustainability guidelines were met.

Access Floor System Used

Steel Cementitious Ultrafix System with a 3.0kN load rating at 150mm FFH

Product Code: SC-3.0-UF